If your scaffold touches a pavement, road or verge, you need a scaffolding licence from the council before it goes up. Most scaffolders know that. What catches people out is the insurance condition attached to it.
Every council asks to see public liability insurance before it will issue a licence. The amount it asks for is not the same everywhere. Islington wants £10 million. Wandsworth, a few miles away, asks for £5 million. Some councils also want the policy to protect the council itself, not only your business.
This matters for two reasons. If your cover is too low for the borough, your application can be refused or delayed. If your policy lapses while the scaffold is still up, some councils treat the licence as invalid from that point. You then have an unlicensed structure on the highway.
This guide explains how a scaffolding licence works, what five London boroughs ask for, and what to check with your broker before you apply. Council rules change, so treat the figures as a starting point and check the council’s own page before each job.
What a scaffolding licence is and why the council asks for insurance
A scaffolding licence (sometimes called a scaffold licence or scaffolding permit) is permission from the highway authority to put a structure on or over the public highway. It comes from Section 169 of the Highways Act 1980. The highway includes pavements and grass verges as well as the road.
In London, the highway authority is usually the borough council. Outside London, it is often the county or unitary council.
Who applies
In most areas, the scaffolding company applies, not the homeowner or builder. Hampshire County Council, for example, says scaffolding companies must apply on behalf of their customers. This means the licence, and the insurance behind it, sits with you.
Why insurance is a condition
A scaffold on a public pavement puts the public at risk. A dropped fitting, a loose board or a collapse can injure a passer-by or damage a parked car. The council is the highway authority, so it can be pulled into a claim too. Asking for public liability insurance is how councils make sure there is money to pay for that harm.
What London boroughs ask for: a comparison
Here is what five London councils say on their current licence pages and forms.
| Borough | Minimum Public Liability | Other Insurance Conditions |
|---|---|---|
| Islington | £10 million | The council must be indemnified against claims caused by the scaffold. No insurance means the licence becomes invalid. |
| Newham | £10 million | Public and employers’ liability documents are required with the application. |
| Wandsworth | £5 million | The certificate must be valid for the whole licence period. Apply at least 5 working days before you need it. |
| Merton | £5 million | Licences are only issued to contractors or scaffold companies with this cover. |
| Hammersmith & Fulham | £5 million | Applications are accepted from scaffolding companies only. |
Sources: each council’s scaffolding licence page or application form, checked October 2026.
Outside London, £10 million is common. Hampshire, Lincolnshire, Wokingham and West Berkshire all ask for at least £10 million. West Berkshire also says the policy should indemnify the council up to £10 million for third-party claims.
What the numbers tell you
There is no single national figure. A firm with £5 million cover can get a licence in Wandsworth or Merton but would not meet Islington’s condition. If you work across several boroughs, your cover needs to match the highest figure you are likely to meet, not the borough you work in most.
What “indemnify the council” means
Some councils ask for more than a minimum limit. They want the policy to cover the council if a claim is made against it because of your scaffold.
Insurers often call this an indemnity to principal clause. It means that if a member of the public sues the council over an injury caused by your scaffold, your policy can respond on the council’s behalf as well as yours.
Not every policy includes this as standard, and wording varies. If a council asks for it, check your schedule or ask your broker to confirm in writing. Some councils will want to see the wording, not just a certificate with a limit on it.
What happens if your cover lapses mid-job
This is where scaffolders are most exposed. A licence often runs for weeks or months. A policy might renew halfway through.
Islington’s licence conditions say that failing to have insurance makes the licence invalid. Wandsworth asks for a certificate that is valid for the whole licence period. In practice, that means:
- If your policy renews during the licence, send the new certificate to the council straight away.
- If your cover lapses, even for a few days, the scaffold may be on the highway without a valid licence.
- If something happens during that gap, you could face a claim with no cover and a licence breach at the same time.
The cost of an unlicensed scaffold
Councils do prosecute. Enfield’s application form warns that putting scaffolding up without a licence can lead to prosecution under Section 169 and a fine of up to £5,000. In 2024, Anglesey County Council took two scaffolding firms to court over an unlicensed scaffold in Beaumaris, and magistrates found them guilty. Merton says it will recover its costs from the scaffold company if an unlicensed structure has to be dealt with.
Before you apply: a scaffolding licence checklist

Most councils ask for a similar set of documents. Having them ready saves time.
- A public liability certificate showing the limit, the policy dates and the insured name. Southwark says the applicant must be the same as the policyholder, with matching details.
- Confirmation that the policy covers the council where required.
- A site plan or sketch showing the scaffold footprint and pavement width.
- Risk assessment and method statement if the council asks for them.
- Proof of competence, such as membership of a recognised scaffolding body, where required.
- The fee. Merton, for example, charges £403 a month for a residential scaffold up to 10 metres.
Allow enough notice. Wandsworth asks for 5 working days. Other councils ask for 7 to 10 working days. If the scaffold is on a red route, you also need permission from Transport for London.
Questions to ask your broker
- What is my public liability limit, and can it be raised for a single contract or for the whole year?
- Does my policy include an indemnity to principal clause?
- When does my policy renew, and will the new certificate be ready before my current licences run out?
Our earlier guide on scaffolding regulations covers the wider safety rules that sit alongside licensing.
Match your cover to the borough before the scaffold goes up
A scaffolding licence is a council permit, but in practice it depends on your insurance. Councils set different limits, from £5 million in Wandsworth and Merton to £10 million in Islington, Newham and many county areas. Some also want the council protected under your policy.
The safest approach is to check the council’s page for every new job, keep your certificate up to date with every council where you hold a live licence, and make sure your limit covers the strictest borough you work in. If your current cover falls short, sort it out before you apply, not after the council rejects the application.
If you would like to check your current limits, speak to our team about scaffolders insurance or request a quote.